This month we are happy to share the Go Long Wireless Installation Schedule. This schedule provides a better understanding of where we currently stand and the anticipated dates of completion for each city. This schedule is based on a six week installation plan commencing the first week of May, with 80% of all links installed within the first three weeks. Final installation along with any punch-list items are scheduled to be completed by the second week of June.
As more information becomes available I will continue to share. Stay tuned for further updates.